On-site installation service for the international coil packing line projects

Precision Engineered On-Site Installation & Commissioning Subheadline: From site readiness to final handover, we ensure your Steel Coil Packing Line is installed to international safety standards and seamlessly integrated with your ERP & MES systems.

CE Certified
ISO 9001
2 Year Warranty
On-site installation service for the international coil packing line projects

On-site installation service for the international coil packing line projects

On-Site Engineering Service

Engineering Excellence:
Comprehensive Guide to Our On-Site Installation & Commissioning Service

At FHOPEPACK, we understand that purchasing a Steel Coil Packing Line is only half the investment; the other half is ensuring it is installed, integrated, and commissioned to operate at peak efficiency. Our on-site service is not just about assembling parts—it is a rigorous engineering process governed by ISO 9001 quality standards and IEC 60204-1 safety protocols.

This document outlines our standardized workflow, from engineer deployment to final system acceptance, ensuring transparency and technical precision at every step.

01

Phase 1: Engineer Arrangement & Pre-Deployment

Before our team sets foot on your site, we initiate a thorough preparation phase to ensure resource readiness and safety compliance.

The Technical Team

We do not send generic laborers. We deploy a specialized cross-functional team tailored to your specific system configuration (e.g., 1-3T Capacity Lines).

Installation Lead

Responsibility
Project coordination, schedule adherence, customer liaison.
Qualification
Engineering Degree, Project Management exp.

Mech. Technician

Responsibility
Assembly, alignment, hydraulic/pneumatic connection.
Qualification
Certified Millwright/Fitter, Rigging certs.

Elec. Technician

Responsibility
Control panel wiring, field device connection, IO checks.
Qualification
Licensed Electrician, IEC 60204-1 expert.

Controls Engineer

Responsibility
PLC/HMI programming, MES data integration, debugging.
Qualification
Automation Engineering Degree, PLC Specialist.

Pre-Site Documentation

Prior to travel, we share the following for your review:

Site-Specific Risk Assessment (ISO 12100)
Identifying hazards (lifting, electrical, stored energy).
Gantt Chart Itinerary
A day-by-day breakdown of activities.
Utility Requirements
Detailed specs for Power, Compressed Air, and Ethernet availability.
02

Phase 2: On-Site Installation Execution

Upon arrival, our focus shifts to physical assembly and precision alignment. We follow a strict "Safety First" approach, implementing Lockout/Tagout (LOTO) procedures immediately.

1. Mechanical Installation

We install major components sequentially to maintain site logic and flow.

Turnstile & Coil Tilter
Action: Anchor mounting and leveling (+/- 5mm tolerance).
Check: Alignment with upstream production lines to ensure smooth coil transfer.
Packing Machine (Stretch Wrapper)
Action: Ring/arm assembly and film carriage calibration.
Check: Parallelism of support rollers to prevent film breaks.
Hydraulics & Pneumatics
Action: Leak-free connection of all hoses and valves.
Check: System pressure verification against P&ID diagrams.

2. Electrical & Safety Installation

All wiring is executed in strict accordance with IEC 60204-1.

Control Panels

Secure mounting and verification of environmental rating (IP54/NEMA 12).

Field Wiring

Separation of power cables (VFD outputs) and signal cables (Ethernet/Sensors) to prevent EMI noise.

Safety Devices (ISO 13849)
  • Installation of E-Stops (Dual-channel wiring).
  • Light Curtains: Precise optical alignment and safety distance calculation.
  • Interlock Switches: Non-contact coded magnet installation on all guard doors.

Installation Phase: Rigorous adherence to safety and mechanical standards.

03

Phase 3: Commissioning & System Integration

Once physical installation is complete, we move to the "Logic Phase." This is where the machine comes to life.

01

Step 1: Pre-Commissioning Checklists

We never energize the system without verification.

  • Mechanical: Fastener torque checks, lubrication verification, freedom of movement checks.
  • Electrical: Continuity tests, Insulation Resistance testing (>1 MΩ at 500VDC), Grounding/Bonding integrity.
02

Step 2: Functional Testing (Component Level)

We test each module individually before full integration.

  • Motors: Direction and speed control verification.
  • Sensors: I/O mapping verification on the HMI.
  • Data Interface: Establishing OPC UA / Modbus TCP links with your MES/ERP system for real-time data exchange (Order IDs, Weights, Status).
03

Step 3: Integrated System Testing (Dry Run)

We run the full automatic sequence without a load to verify logic flow, timer settings, and interlocks between stations (e.g., ensuring the Tilter doesn't rotate until the Wrapper is ready).

04

Phase 4: Performance Acceptance Testing (PAT)

This is the final exam. We prove the machine meets the guaranteed performance metrics using your actual production coils (1-3T).

We verify the following KPIs during the PAT run:

Metric Target Value Verification Method
Throughput 20 Coils/Hour Continuous run counting processed coils.
Cycle Time 180 Seconds/Coil Time measurement from entry to discharge.
Packing Quality < 2% Defect Rate Visual inspection of film tension and sealing.
Weighing Accuracy +/- 0.1% Comparison against calibrated test weights.
System Availability > 95% (Total Run Time - Fault Time) / Total Run Time.
05

Phase 5: Troubleshooting & Final Handover

We believe in leaving you with a solution, not just a machine.

Issue Resolution (The Punch List)

During commissioning, any non-conformities are logged in a shared Issues Log.

  • Categorization: Mechanical, Electrical, Software, or Safety.
  • Resolution: We do not leave the site until critical "Punch List" items are resolved and signed off.

Training & Documentation

We provide hands-on training for your operators and maintenance staff, focusing on:

  1. Operation: HMI navigation, recipe management, and auto-recovery.
  2. Maintenance: Lubrication schedules and sensor cleaning.
  3. Safety: Emergency procedures and LOTO zones.

The Final Handover Package Includes:

  • As-Built Drawings
    Electrical & Mechanical
  • O&M Manuals
    For all OEM components
  • Validation Certificates
    Signed PAT Reports & Safety Validation
  • Software Backup
    PLC/HMI Source Code

Why This Process Matters

Our structured On-Site Installation Service minimizes downtime and maximizes the lifespan of your equipment. By adhering to international standards and a transparent acceptance protocol, we ensure that your coil packing line is a reliable asset from Day 1.

Have questions about our installation timeline? Contact Our Engineering Team

Visual Details

On-site installation service for the international coil packing line projects - Detail 1

Click to enlarge

On-site installation service for the international coil packing line projects - Detail 2

Click to enlarge

On-site installation service for the international coil packing line projects - Detail 3

Click to enlarge

On-site installation service for the international coil packing line projects - Detail 4

Click to enlarge

See It In Action

Watch How It Works

Discover how our automated packaging solutions optimize your production line efficiency. This video demonstrates the seamless operation designed for maximum protection.

High Throughput
Up to 60 coils per hour
Consistent Quality
Every wrap meets spec
Request A Quote

Trusted by Steel Mills & Industry Leaders

Global manufacturers rely on FHOPE heavy duty packaging equipment

ArcelorMittal POSCO Nippon Steel Nucor Tata Steel ArcelorMittal POSCO Nippon Steel Nucor Tata Steel

Ready to optimize your packaging line?

Get a custom quote with ROI analysis. Our engineers respond within 24 hours.

  • Free layout design
  • Global installation support
  • 2-year warranty included

Your information is secure and will never be shared.

Related Machines

Autobag for Commercial Laundry Services

Autobag for Commercial Laundry Services

View Details →
What after service you will have for Copper strip packing lin

What after service you will have for Copper strip packing lin

View Details →
After Sale Service for the coil wrapping machine

After Sale Service for the coil wrapping machine